1.1
Definition of Estimate
The process of calculating approximate
cost and quantities of various items required in construction work, for satisfactory
completion is known as Estimation.
1.2
Importance of Estimate
(a) Estimate given idea of cost the work.
(b) Estimate is necessary to determine the quantities of construction
work.
(c) It is done for the administrative approval for public work.
(d) It is also necessary on property valuation work.
(e) It prepares bill of quantities and bill for payment.
(f) Estimate is also required to control the expenditure during the
execution of the work.
(g) It
is required for the preparing tenders for the project.
(h) It is necessary to find the number of worker, tools and equipment
for the completion of the project.
(i) The estimate is necessary for fixing the budget for the project.
1.3
Types of Estimate
·
Preliminary
Estimate
·
Detailed
Estimate
·
Revised
Estimate
·
Supplement
Estimate
·
Revised and
supplement Estimate
·
Complete
Estimate
·
Cube area Estimate
·
Plinth area
Estimate
· Repair and Manitenance Estimate
Explain:
(a)Preliminary Estimate
The estimate is generally prepared initial
stage to known the approximate estimate calculate by comparing the previous
experience or similar type of project.
It is used to obtain administrative approved. It is also called rough estimate or
approximate estimate.
(b)
Plinth
area Estimate
Plinth area
estimate by multiplying plinth area of building with plinth area rate. In this
method plinth area should be calculate by taking internal dimension of the
building at the plinth level. Plinth area estimate =
Plinth area*plinth area rate
(c) Revised Estimate
It is detailed estimate and is prepared a
fresh, when the original sanction detailed estimate exceeds by 5% or more,
either due to rates being found the sufficient or due to some other reasons.
(d)
Cube area
estimate
In this
method the cost of structure is calculated approximately as the total cubical content (volume
of building) multiplying by local cube rate. It is more suitable for
multi-storied building. This method of estimate is accurate than plinth area
estimate.
(e)
Detailed
estimate/Item rate estimate
The estimate is an accurate and is based on the plan sanction of the building. The quantities of item under each sub-head of the work are calculates from the dimension taken from drawing and then total cost is work out on from called abstract cost. The rate of different item of work area taken as per schedule or rate or analysed rates for finished item of work. A percentage 3 to 5% as add as contingency for unseen item ad 2 to 3% is added as work charge establishment.
(f) Revised Estimate
It is detailed estimate and is prepared a fresh, when the original sanction detailed estimate exceeds by 5% or more, either due to rates being found the sufficient or due to some other reasons.
(g) Supplementary Estimate
This
is fresh detailed estimate of the additional work in additional one and
prepared when the additional work is required to supplement the original work.
(h) Repair and maintenance Estimate
The
estimate are prepared in order to maintain the constructed structure in good
condition. Work that are considered repair estimate may be white washing,
painting, plastering work, patching work etc.

Comments
Post a Comment